Gardenia

Gardenia is a 46.5 MW solar + storage request in interconnection study in the PJM interconnection queue, in Clarion County, Pennsylvania, connecting to APS.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AG2-429
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Developer
Gardenia Solar, LLC
Connection point (POI)
Burma - Armstrong 138 kV
Location
Clarion County, Pennsylvania
Technology
Solar: 46.5 MW · Battery
Total requested
46.5 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
26 February 2025
Proposed online date
February 2024

Location

Marker shows the centre of Clarion County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Clarion County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem