United States › Grid › Interconnection queues › Pennsylvania

GAS · PJM

Clarion Boards

Clarion Boards is a 18.0 MW gas request built and operating in the PJM interconnection queue, in Clarion County, Pennsylvania, connecting to PENELEC.

Queue statusOperating
  1. PlanningQueued Sep 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingNov 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AE1-123
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
Emlenton 34.5 kV
Location
Clarion County, Pennsylvania
Technology
Gas: 18.0 MW
Total requested
18.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Operational
Entered queue
20 September 2018
Proposed online date
November 2023
Came online
November 2023

Location

Marker shows the centre of Clarion County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Clarion County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem