United States › Grid › Interconnection queues › Pennsylvania

SOLAR · PJM

Solar project AH2-128, Clarion County

Solar project AH2-128, Clarion County is a 8.0 MW solar request in interconnection study in the PJM interconnection queue, in Clarion County, Pennsylvania, connecting to APS.

Queue statusIn planning
  1. PlanningQueued Feb 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH2-128
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Stone Solar 34.5 kV
Location
Clarion County, Pennsylvania
Technology
Solar: 8.0 MW
Total requested
8.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
28 February 2022
Proposed online date
May 2026

Location

Marker shows the centre of Clarion County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Clarion County