United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in the USA (2021 requests) — page 14
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery storage project 624, Jerome County Battery storage · Gem Vale Energy Storage LLC |
100 MW | Paused / redesign |
| Battery storage project J2026, Gratiot County Battery storage |
100 MW | In study |
| Solar + storage project J2057, Montcalm County Solar + storage |
100 MW | In study |
| Battery storage project J2232, Tipton County Battery storage |
100 MW | In study |
| Solar project G0706, Morrow County Solar |
100 MW | In study |
| Solar project J2297, Sunflower County Solar |
100 MW | In study |
| Solar project AH2-010, Logan County Solar |
100 MW | In study |
| Onshore wind project J2031, Tama County Onshore wind |
100 MW | In study |
| Solar project J1932, Gladwin County Solar |
100 MW | In study |
| Solar project J1904, Acadia Parish County Solar |
100 MW | In study |
| Battery storage project J2066, Henry County Battery storage |
100 MW | In study |
| Solar + storage project J2133, White County Solar + storage |
100 MW | In study |
| Solar project LGE-GIS-2021-019, Boyle County Solar |
100 MW | Paused / redesign |
| Backwater Storage Battery storage |
100 MW | Paused / redesign |
| Solar + storage project Company 209, Clark County Solar + storage |
100 MW | Paused / redesign |
| Onshore wind project J2097, Morton County Onshore wind |
100 MW | In study |
| Battery storage project GEN-2021-088, Cleveland County Battery storage |
100 MW | In study |
| Solar + storage project J2069, Montcalm County Solar + storage |
100 MW | In study |
| Battery storage project Q372, Maricopa County Battery storage |
100 MW | In study |
| Battery storage project J2120, Linn County Battery storage |
100 MW | In study |
| Solar project IC-1005, Burke County Solar |
100 MW | Paused / redesign |
| Solar project J1514, Mississippi County Solar |
100 MW | Under construction |
| Bordertown BESS Battery storage |
100 MW | Paused / redesign |
| Solar + storage project IC-980, Oglethorpe County Solar + storage |
100 MW | Paused / redesign |
| Solar project G0713, Morrow County Solar |
100 MW | In study |
| Solar + storage project C1-27, Benton County Solar + storage · Solway Solar Energy LLC |
100 MW | Paused / redesign |
| Solar + storage project J2193, Waushara County Solar + storage |
100 MW | In study |
| Battery storage project 15, Sacramento County Battery storage |
100 MW | In study |
| Sunsetter BESS Battery storage · CED Development Inc. |
100 MW | In study |
| Solar project J1993, Columbia County Solar |
99.0 MW | In study |
| Solar project J2208, De Soto Parish County Solar |
99.0 MW | In study |
| Leitrim 1 Solar Solar · Leitsol LLC |
98.4 MW | In study |
| Midpoint Solar Solar · Midpoint Solar, LLC |
98.3 MW | Agreement signed |
| Onshore wind project GI-96, Lincoln County Onshore wind |
97.5 MW | Agreement signed |
| Agricola Wind Onshore wind · Agricola Wind LLC |
97.0 MW | In study |
| Rocinante Solar Solar + storage · Brush Country Solar Project, LLC |
95.3 MW | Agreement signed |
| Solar + storage project GEN-2021-077, Pettis County Solar + storage |
95.0 MW | In study |
| High Noon Storage Solar + storage · High Noon Solar Project, LLC |
94.0 MW | Agreement signed |
| Rosscommon Solar Solar · Roscsol, LLC |
91.0 MW | In study |
| Solar project AH2-030, Jefferson County Solar |
90.0 MW | In study |
| Solar project J1827, Morehouse Parish County Solar |
90.0 MW | Agreement signed |
| North Seneca Solar Project, LLC Solar · North Seneca Solar Project |
90.0 MW | In study |
| Solar + storage project GI-2021-148, Imperial County Solar + storage |
90.0 MW | In study |
| York Run Solar Solar · York Run Solar, LLC |
90.0 MW | In study |
| Battery storage project 124, Pierce County Battery storage |
85.0 MW | Paused / redesign |
| Payne Battlecreek Solar · Gransolar Texas Ten, LLC |
85.0 MW | Agreement signed |
| Lupinus Storage 1 Solar + storage · Lupinus Solar, LLC |
84.0 MW | In study |
| Harper Energy Storage Battery storage · VESI 31 LLC |
82.4 MW | In study |
| Sunbelt Solar Solar + storage · Rose Hill Solar LLC |
81.5 MW | In study |
| Long Cane Solar Solar + storage |
80.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)228 · 68.8 GW
- CAISO (California)138 · 66.9 GW
- ERCOT (Texas)207 · 39.5 GW
- MISO (Midcontinent)136 · 23.7 GW
- Southeast (non-ISO utilities)63 · 12.7 GW
- SPP (Southwest Power Pool)44 · 9,029 MW
- ISO-NE (New England)20 · 3,998 MW
- PJM (Mid-Atlantic, Midwest)49 · 2,072 MW
- NYISO (New York)11 · 991 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)