United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTRosscommon Solar
Rosscommon Solar is a 91.0 MW solar request in interconnection study in the ERCOT interconnection queue, in Lamar County, Texas.
Queue statusIn planning
- PlanningQueued Mar 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 23INR0211
- Grid region
- ERCOT (Texas)
- Developer
- Roscsol, LLC
- Connection point (POI)
- tap 138kV 1691 Valley Switch - 1776 Paris Switch
- Location
- Lamar County, Texas
- Technology
- Solar: 91.0 MW
- Total requested
- 91.0 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 1 March 2021
- Proposed online date
- April 2027
Location
Marker shows the centre of Lamar County; the queue data does not give exact sites.
Other requests in Lamar County
- Baker Branch SolarSolar · 469 MW · agreement signed
- Bug Tussle Wind ProjectOnshore wind · 397 MW · agreement signed
- Rowdy Creek SolarSolar + storage · 352 MW · agreement signed
- Delilah Solar 2Solar · 318 MW · agreement signed
- Delilah Solar 1Solar · 300 MW · agreement signed
- Samson Solar 3Solar · 250 MW · agreement signed
- Samson Solar 1Solar · 250 MW · agreement signed
- Star Dairy StorageSolar + storage · 205 MW · agreement signed
- Samson Solar 2Solar · 203 MW · agreement signed
- Echols Grove, LLCSolar · 201 MW · agreement signed
- Rowdy Creek BESSSolar + storage · 176 MW · agreement signed
- MRG Goody SolarSolar + storage · 171 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem