🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA (2024 requests) — page 13

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,283285.2 GW
Active in queue285.2 GW1,283 requests
Agreement signed30.3 GW117 requests
Withdrawn1,313251.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,283 requests · page 13 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J3480, Allegan County
Battery storage
200 MWIn study Allegan, MIMISO Apr 2024target 2026
Battery storage project GEN-2024-092, Roosevelt County
Battery storage
200 MWIn study Roosevelt, NMSPP Oct 2024target 2029
Overlook Storage
Battery storage · Origis Development LLC
199 MWIn study Dutchess, NYNYISO Oct 2024target 2028
Battery storage project PIS088, Salt Lake County
Battery storage
199 MWIn study Salt Lake, UTWest Sep 2024target 2028
Solar + storage project GI-2024-01, Weld County
Solar + storage
199 MWIn study Weld, COWest Apr 2024target 2027
Solar + storage project 5RSC-2024-24, Adams County
Solar + storage
199 MWIn study Adams, COWest Jan 2024target 2027
Solar + storage project GI-2024-20, Lincoln County
Solar + storage
199 MWIn study Lincoln, COWest May 2024target 2028
Battery storage project GI-2024-09, Adams County
Battery storage
199 MWIn study Adams, COWest May 2024target 2027
Solar + storage project GI-2024-19, Lincoln County
Solar + storage
199 MWIn study Lincoln, COWest May 2024target 2028
Battery storage project FC100009, Pasco County
Battery storage · Duke Energy Florida, LLC
199 MWIn study Pasco, FLSoutheast Dec 2024target 2029
Solar + storage project GI-2024-02, Weld County
Solar + storage
199 MWIn study Weld, COWest Apr 2024target 2027
Battery storage project 5RSC-2024-13, Weld County
Battery storage
199 MWIn study Weld, COWest Jan 2024target 2027
Battery storage project 956141, Gaston County
Battery storage
199 MWIn study Gaston, NCSoutheast Jun 2024
Solar project GI-TC-2024-10, Kit Carson County
Solar
199 MWIn study Kit Carson, COWest May 2024target 2028
Onshore wind project J3566, Mclean County
Onshore wind
198 MWIn study Mclean, ILMISO Apr 2024target 2028
Solar project GEN-2024-GR3, Lea County
Solar
196 MWIn study Lea, NMSPP Jun 2024target 2027
Johnson Grass Solar
Solar · Johnson Grass Solar ,LLC
196 MWIn study Mitchell, TXERCOT Oct 2024target 2028
Onshore wind project J3753, Iroquois County
Onshore wind
196 MWIn study Iroquois, ILMISO Apr 2024target 2028
Solar project J3801, Mercer County
Solar
196 MWIn study Mercer, ILMISO Apr 2024target 2028
Onshore wind project GEN-2024-089, Curry County
Onshore wind
195 MWIn study Curry, NMSPP Oct 2024target 2029
SR Wrens
Solar
194 MWIn study Jefferson, GASoutheast Dec 2024target 2029
Paloma Energy Center
Solar + storage · Harrison Street Development, LLC
194 MWIn study Colorado, TXERCOT Feb 2024target 2027
Onshore wind project J3292, Phillips County
Onshore wind
193 MWIn study Phillips, ARMISO Apr 2024target 2028
Steelhead Energy Storage
Battery storage · GRS BESS TEXAS SEVEN, LLC
192 MWIn study Fannin, TXERCOT Feb 2024target 2027
Solar project J3353, Champaign County
Solar
191 MWIn study Champaign, ILMISO Apr 2024target 2028
Malachite BESS
Solar + storage · Malachite Storage LLC
191 MWIn study Wharton, TXERCOT May 2024target 2029
Bullring Wind 3
Onshore wind · Halcon Wind, LLC
190 MWAgreement signed Starr, TXERCOT May 2024target 2028
Battery storage project J3517, Williamson County
Battery storage
190 MWIn study Williamson, ILMISO Apr 2024target 2028
Solar project J3686, Christian County
Solar
190 MWIn study Christian, ILMISO Apr 2024target 2028
Battery Park Storage
Battery storage · Battery Park Storage LLC
190 MWIn study Kings, NYNYISO Aug 2024target 2028
Chacon Creek
Battery storage · Cattlemen BESS LLC
189 MWIn study Medina, TXERCOT Mar 2024target 2027
Gas project 153, Skagit County
Gas
188 MWIn study Skagit, WAWest Apr 2024target 2028
Gas project 152, Whatcom County
Gas
188 MWIn study Whatcom, WAWest Apr 2024target 2028
Solar project 267, Saluda County
Solar
186 MWIn study Saluda, SCSoutheast Jun 2024target 2028
Solar project J1518, Vermillion County
Solar
185 MWIn study Vermillion, INMISO Aug 2024target 2026
Los Vientos IB Repower
Onshore wind · Los Vientos Windpower IB, LLC
185 MWIn study Willacy, TXERCOT Jul 2024target 2027
Malachite Solar
Solar + storage · Malachite Solar LLC
185 MWIn study Wharton, TXERCOT Feb 2024target 2029
Cairos Storage 2
Battery storage · Cairos Solar, LLC
184 MWIn study Kinney, TXERCOT Jul 2024target 2026
Jalisco Peaker
Gas · HEP Power Generation, LLC
184 MWIn study Nueces, TXERCOT Aug 2024target 2029
Basketflower Solar
Solar + storage · Basketflower Solar, LLC
183 MWIn study Eastland, TXERCOT Oct 2024target 2027
Nanulak BESS
Battery storage · Nanulak BESS, L.L.C.
182 MWIn study Reeves, TXERCOT Mar 2024target 2027
Turkey Creek Solar SLF
Solar + storage · Greenray Solar Corporation
181 MWIn study Kinney, TXERCOT Feb 2024target 2026
Amphion Solar Phase 1
Solar · Amphion Solar, LLC
181 MWIn study Atascosa, TXERCOT Oct 2024target 2028
Battery storage project J3782, Saginaw County
Battery storage
180 MWIn study Saginaw, MIMISO Apr 2024target 2027
Onshore wind project J3448, Grant County
Onshore wind
180 MWIn study Grant, WIMISO Apr 2024target 2028
Elevate Arthur Kill II
Battery storage · Lighthouse Arthur Kill II, LLC
180 MWIn study Richmond, NYNYISO Sep 2024target 2028
Whitetail BESS
Battery storage · Hunt Energy Network, LLC
180 MWIn study Mitchell, TXERCOT Feb 2024target 2027
Battery Storage
Battery storage
180 MWIn study Worcester, MAISO-NE May 2024target 2028
Onshore wind project J3702, Mitchell County
Onshore wind
180 MWIn study Mitchell, IAMISO Mar 2024target 2028
Lockport Storage
Battery storage · Origis Development LLC
180 MWIn study Niagara, NYNYISO Oct 2024target 2028
Page 13 of 26

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)