United States βΊ Grid βΊ Interconnection queues βΊ Texas
GAS Β· ERCOTJalisco Peaker
Jalisco Peaker is a 184 MW gas request in interconnection study in the ERCOT interconnection queue, in Nueces County, Texas.
Queue statusIn planning
- PlanningQueued Aug 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 28INR0121
- Grid region
- ERCOT (Texas)
- Developer
- HEP Power Generation, LLC
- Connection point (POI)
- 8475 JAVELINA4A 138kV
- Location
- Nueces County, Texas
- Technology
- Gas: 184 MW
- Total requested
- 184 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 16 August 2024
- Proposed online date
- May 2029
Location
Marker shows the centre of Nueces County; the queue data does not give exact sites.
Other requests in Nueces County
- Sunscape Renewable Energy Solar SLFSolar + storage Β· 523 MW Β· agreement signed
- NavBoot BESSBattery storage Β· 304 MW Β· agreement signed
- Blanquilla BESSBattery storage Β· 201 MW Β· agreement signed
- Project Lynx BESSBattery storage Β· 125 MW Β· agreement signed
- Lantana BESSBattery storage Β· 10.0 MW Β· agreement signed
- Olympic BESSBattery storage Β· 223 MW Β· in study
- BRP Perseus BESSBattery storage Β· 203 MW Β· in study
- Sengun BESSBattery storage Β· 201 MW Β· in study
- Barbara BESSBattery storage Β· 201 MW Β· in study
- Jalisco CogenGas Β· 168 MW Β· in study
- SunWave SolarSolar Β· 154 MW Β· in study
- Gotham BESSBattery storage Β· 151 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem