United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTSunscape Renewable Energy Solar SLF
Sunscape Renewable Energy Solar SLF is a 523 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Nueces County, Texas.
Queue statusConsented
- PlanningQueued Jun 2023 (completed)
- ConsentedJul 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Jan 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 27INR0047
- Grid region
- ERCOT (Texas)
- Developer
- Sunscape Renewable Energy LLC
- Connection point (POI)
- Bus# 8455 Lon C Hill to Bus# 80078 Reforzar 345 kV Line
- Location
- Nueces County, Texas
- Technology
- Solar: 523 MW · Battery
- Total requested
- 523 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 28 June 2023
- Agreement signed
- 18 July 2024
- Proposed online date
- January 2029
Location
Marker shows the centre of Nueces County; the queue data does not give exact sites.
Other requests in Nueces County
- NavBoot BESSBattery storage · 304 MW · agreement signed
- Blanquilla BESSBattery storage · 201 MW · agreement signed
- Project Lynx BESSBattery storage · 125 MW · agreement signed
- Lantana BESSBattery storage · 10.0 MW · agreement signed
- Olympic BESSBattery storage · 223 MW · in study
- BRP Perseus BESSBattery storage · 203 MW · in study
- Sengun BESSBattery storage · 201 MW · in study
- Barbara BESSBattery storage · 201 MW · in study
- Jalisco PeakerGas · 184 MW · in study
- Jalisco CogenGas · 168 MW · in study
- SunWave SolarSolar · 154 MW · in study
- Gotham BESSBattery storage · 151 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem