🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Los Vientos IB Repower

Los Vientos IB Repower is a 185 MW onshore wind request in interconnection study in the ERCOT interconnection queue, in Willacy County, Texas.

Queue statusIn planning
  1. PlanningQueued Jul 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0507
Grid region
ERCOT (Texas)
Developer
Los Vientos Windpower IB, LLC
Connection point (POI)
#8319 RIOHONDO 138 kV
Location
Willacy County, Texas
Technology
Wind: 185 MW
Total requested
185 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
22 July 2024
Proposed online date
March 2027

Location

Marker shows the centre of Willacy County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Willacy County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem