ONSHORE WIND · ERCOT

West Raymond (Trueno) Wind

West Raymond (Trueno) Wind is a 240 MW onshore wind request built and operating in the ERCOT interconnection queue, in Willacy County, Texas.

Queue statusOperating
  1. PlanningQueued May 2018 (completed)
  2. ConsentedMay 2019 (completed)
  3. Construction (completed)
  4. OperatingOct 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0088
Grid region
ERCOT (Texas)
Developer
Eon
Connection point (POI)
tap 345kV 8318 Rio Hondo - 8383 N Edinburg
Location
Willacy County, Texas
Technology
Wind: 240 MW
Total requested
240 MW
Study phase
IA
Queue status
Operational
Entered queue
13 May 2018
Agreement signed
20 May 2019
Proposed online date
November 2021
Came online
October 2021

Location

Marker shows the centre of Willacy County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Willacy County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem