Solar + storage project GI-2024-02, Weld County

Solar + storage project GI-2024-02, Weld County is a 199 MW solar + storage request in interconnection study in the West interconnection queue, in Weld County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-2024-02
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Canal Crossing - Ft St Vrain 345 kV line
Location
Weld County, Colorado
Technology
Solar: 199 MW · Battery
Total requested
199 MW
Service type
Network resource (NRIS)
Study phase
Detailed status: Study to be started after completion of 5RSC
Queue status
Active
Entered queue
5 April 2024
Proposed online date
May 2027

Location

Marker shows the centre of Weld County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Weld County