United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Cairos Storage 2

Cairos Storage 2 is a 184 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Kinney County, Texas.

Queue statusIn planning
  1. PlanningQueued Jul 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0448
Grid region
ERCOT (Texas)
Developer
Cairos Solar, LLC
Connection point (POI)
7425 ODLAW SWITCH 138kV
Location
Kinney County, Texas
Technology
Battery: 184 MW
Total requested
184 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
1 July 2024
Proposed online date
December 2026

Location

Marker shows the centre of Kinney County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Kinney County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem