United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTZier Solar
Zier Solar is a 163 MW solar request built and operating in the ERCOT interconnection queue, in Kinney County, Texas.
Request details
- Queue ID
- 21INR0019
- Grid region
- ERCOT (Texas)
- Developer
- Zier Solar, LLC
- Connection point (POI)
- 78255 Pinto Creek 138kV
- Location
- Kinney County, Texas
- Technology
- Solar: 163 MW
- Total requested
- 163 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 23 May 2018
- Agreement signed
- 22 October 2020
- Proposed online date
- April 2024
- Came online
- April 2024
Location
Marker shows the centre of Kinney County; the queue data does not give exact sites.
Other requests in Kinney County
- DeSpain Solar ProjectSolar Β· 236 MW Β· in study
- Longday Solar SLFSolar + storage Β· 201 MW Β· in study
- Cairos Storage 2Battery storage Β· 184 MW Β· in study
- Turkey Creek Solar SLFSolar + storage Β· 181 MW Β· in study
- Cairos SolarSolar + storage Β· 153 MW Β· in study
- Kinney County EnergyBattery storage Β· 101 MW Β· in study
- Las Moras BatteryBattery storage Β· 101 MW Β· in study
- Galvanic BESSBattery storage Β· 100 MW Β· in study
- Cairos StorageSolar + storage Β· 77.3 MW Β· in study
- Zier StorageOther Β· 40.4 MW Β· built
- Brangus SolarSolar Β· 205 MW Β· withdrawn
- Brangus StorageOther Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem