NESO TEC REGISTER · GREAT BRITAINBattery storage projects in the connection queue on the SP Transmission (south Scotland) network
Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.
Map
Voltage400 kV275 kV132 kVHVDCNew HVAC
ProjectsPlanningConsentedConstructionBuiltMajor project with its own page
Projects
| Project | Capacity | Stage |
|---|---|---|
| Aitkenhead Farm BESS Battery storage · Aitkenhead Storage Facility Limited |
300 MW | Scoping |
| Boom Power Seaton Hill Generation HUB Battery storage · Seatonhill Storage Facility Limited |
300 MW | Scoping |
| Coylton Farm Battery storage · New Energy Partnership Limited |
300 MW | Awaiting Consents |
| Craig Moss Farm Battery storage · Qair Renewables UK Limited |
300 MW | Scoping |
| Crossgatehall BESS Battery storage · De 001 Limited |
300 MW | Scoping |
| Elmya Bathgate BESS Battery storage · Rpc Elmya Carnation Bathgate Limited |
300 MW | Scoping |
| Gresham House Dalmarnock BESS Battery storage · Energyhubdevelopments Limited |
300 MW | Scoping |
| Gresham House Kincardine BESS Battery storage · Flavusia Ltd |
300 MW | Scoping |
| Newarthill Energy Park Battery storage · Dalzell (Newarthill) Ltd |
300 MW | Scoping |
| Red Moss Farm Battery storage · Qair Renewables UK Limited |
300 MW | Scoping |
| Strathaven BESS Battery storage · Igp Energy Storage 2 Limited |
300 MW | Scoping |
| Zenobe Kilmarnock South Battery storage · Zenobe Kilmarnock South Limited |
300 MW | |
| Alcemi Armadale BESS Battery storage · Alcemi Storage Developments 8 Ltd |
280 MW | Scoping |
| KINKHALL266MW BESS BEGA (Kinkell) Battery storage · Care Power (Kinkhall) Limited |
266 MW | Scoping |
| Craigneuk 250MW BESS Battery storage · Apatura Project 23 Ltd |
250 MW | Scoping |
| Greenock Road BESS Battery storage · Pulse Clean Energy Limited |
250 MW | Scoping |
| Hunterston PARC BESS Battery storage · Pulse Clean Energy Limited |
250 MW | Scoping |
| TH Renfrewshire Battery storage · FRV Powertek Limited |
250 MW | Scoping |
| West Caulder BESS Battery storage · GPC Project 13 Ltd |
250 MW | Scoping |
| Bearsden BESS Battery storage · Bearsden BESS Ltd |
240 MW | Scoping |
| Burdiehouse BESS Battery storage · IBV Burdiehouse Energy Park Limited |
240 MW | Scoping |
| Gresham House Cockenzie BESS Battery storage · Cockenzie Storage Limited |
240 MW | Under Construction/Commissioning |
| High Bardrain Wood & Moor Battery storage · Bluestone Energy Ltd |
240 MW | Scoping |
| Torness BESS Station Battery storage · IBV Torness Energy Park Limited |
240 MW | Scoping |
| Bendle Farm Battery storage · Supernova Power BESS Holdings Limited |
228 MW | Scoping |
| Bendle Farm 2.0 Battery storage · Supernova Power BESS Holdings Limited |
228 MW | Scoping |
| Smeaton BESS Battery storage · Kona Asset 3 Limited |
228 MW | Consents Approved |
| Auldhouse 200MW BESS Battery storage · Apatura Project 29 Ltd |
200 MW | Scoping |
| Carberry BESS (was Smeaton BESS) Battery storage · Harmony Cbr Ltd |
200 MW | Scoping |
| Clonmacate Farm BESS Battery storage · GPC Project 11 Ltd |
200 MW | Scoping |
| Field Glenniston BESS Battery storage · Field Devco Ltd |
200 MW | Scoping |
| Fife Battery Storage Battery storage · Carlton Power Limited |
200 MW | Scoping |
| FPE Ayr BESS Battery storage · Future Power Enterprises Ltd |
200 MW | Scoping |
| Garscadden Park Battery storage · Garscadden Park Limited |
200 MW | Scoping |
| Gartclash Farm BESS Battery storage · South Plean Storage Facility Limited |
200 MW | Scoping |
| Giffordland 200Mw Field BESS Battery storage · Virmati Energy Ltd |
200 MW | Scoping |
| Gresham House Mossmoran BESS Battery storage · Mossmorran Energy Storage Limited |
200 MW | Scoping |
| Highview Hunterston East Cryobattery Battery storage · Hvs Siteco Ltd |
200 MW | Consents Approved |
| Hunterston Battery Storage Facility Battery storage · Hunterston Grid 1 Ltd |
200 MW | Consents Approved |
| Hunterston Energy Storage Facility Battery storage · Hunterston Grid 1 Ltd |
200 MW | Consents Approved |
| Kincardine Battery Storage Facility Battery storage · Kincardine Grid 1 Ltd |
200 MW | Consents Approved |
| Kincardine Energy Storage Facility Battery storage · Kincardine Grid 1 Ltd |
200 MW | Consents Approved |
| Kirklands Farm BESS Battery storage · Apatura Battery Ltd |
200 MW | Scoping |
| L48 BESS Glen App Battery storage · S4 UK DEV LTD |
200 MW | Scoping |
| Leslie 200MW BESS Battery storage · Apatura Battery Ltd |
200 MW | Scoping |
| Milligansbush Battery Storage Battery storage · Milligansbush Battery Storage Ltd |
200 MW | Scoping |
| Murroch BESS Battery storage · Apatura Battery Ltd |
200 MW | Scoping |
| North Lanrigg Battery Storage Battery storage · North Lanrigg Battery Storage Ltd |
200 MW | Scoping |
| Pitkevy BESS Battery storage · Harmony Energy Limited |
200 MW | Scoping |
| Pond Flexible Energy Park Battery storage · Pond Flexible Energy Park Limited |
200 MW | Scoping |
Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.