BATTERY STORAGE · SPT

Garscadden Park

Garscadden Park is a 200 MW battery storage project in planning, connecting to the SP Transmission (south Scotland) network at Garscadden Park 275kV Substation, with capacity due from October 2033. The connection agreement is held by Garscadden Park Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2033 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004103
Customer
Garscadden Park Limited
Technology
Energy Storage System
Total capacity
200 MW
Change in this agreement
+200 MW
Capacity effective from
31 October 2033
Connection site
Garscadden Park 275kV Substation
Transmission owner
SP Transmission (south Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The connection site could not be placed on the map.

Projects connecting near Garscadden Park · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem