Gresham House Dalmarnock BESS is a 300 MW battery storage project in planning, connecting to the SP Transmission (south Scotland) network at Gresham House Dalmarnock Bess 132kv Substation, with capacity due from April 2030. The connection agreement is held by Energyhubdevelopments Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Apr 2030 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-002809
- Customer
- Energyhubdevelopments Limited
- Technology
- Energy Storage System
- Total capacity
- 300 MW
- Change in this agreement
- +300 MW
- Capacity effective from
- 30 April 2030
- Connection site
- Gresham House Dalmarnock Bess 132kv Substation
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The connection site could not be placed on the map.
Projects connecting near Gresham House Dalmarnock Bess · Grid map
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem