Grid infrastructure βΊ Connection queue βΊ Battery storage
BATTERY STORAGE Β· SPTBendle Farm
Bendle Farm is a 228 MW battery storage project in planning, connecting to the SP Transmission (south Scotland) network at Bendle Farm 132kV Substation, with capacity due from October 2031. The connection agreement is held by Supernova Power BESS Holdings Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2031 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-002243
- Customer
- Supernova Power BESS Holdings Limited
- Technology
- Energy Storage System
- Total capacity
- 228 MW
- Change in this agreement
- +228 MW
- Capacity effective from
- 31 October 2031
- Connection site
- Bendle Farm 132kV Substation
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem