United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Solar interconnection queue in the USA (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown31843.2 GW
Active in queue43.2 GW318 requests
Agreement signed21.4 GW169 requests
Withdrawn84672.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

318 requests · page 1 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Skylab Solar
Solar · EDF Renewables Development, Inc.
610 MWIn study Wharton, TXERCOT Jun 2020target 2025
Sanborn 5 Hybrid
Solar
560 MWAgreement signed Kern, CACAISO Apr 2020target 2027
Tabor Solar
Solar · Quanah Solar LLC
506 MWIn study Hardeman, TXERCOT Sep 2020target 2027
Solar project GEN-2020-087, Comanche County
Solar
500 MWIn study Comanche, OKSPP Apr 2020target 2026
Baker Branch Solar
Solar · Mockingbird Solar Center, LLC
469 MWAgreement signed Lamar, TXERCOT Mar 2020target 2026
Dolphin Solar
Solar · Dolphin Solar LLC
450 MWIn study Fountain, INPJM Sep 2020target 2024
Solar project GEN-2020-058, Finney County
Solar
425 MWAgreement signed Finney, KSSPP Apr 2020target 2028
Sequoia II Solar
Solar · Deville Solar LLC
418 MWAgreement signed Callahan, TXERCOT Jan 2020target 2026
Caliche Mound Solar
Solar · Tierra Blanco Solar LLC
407 MWAgreement signed Deaf Smith, TXERCOT Jul 2020target 2026
Mineral Basin Solar Power
Solar · Mineral Basin Solar Power, LLC
402 MWIn study Clearfield, PANYISO Aug 2020target 2028
Dorado Solar
Solar · Enbridge Solar (Sequoia I), LLC
401 MWAgreement signed Callahan, TXERCOT Jan 2020target 2026
Oak Run Solar Project
Solar
400 MWAgreement signed Madison, OHPJM Aug 2020target 2030
Oak Run Solar Project
Solar
400 MWAgreement signed Madison, OHPJM Aug 2020target 2030
Solar project G0651, Lake County
Solar
400 MWIn study Lake, ORWest Jul 2020target 2023
Hanson Solar
Solar · Hanson Solar, LLC
399 MWAgreement signed Coleman, TXERCOT Oct 2020target 2027
Charger Solar
Solar · AP Solar 4, LLC
397 MWAgreement signed Refugio, TXERCOT Jun 2020target 2026
Tormes Solar
Solar · BDPU SOLAR TORMES LLC
357 MWAgreement signed Navarro, TXERCOT Oct 2020target 2027
Chillingham Solar
Solar · Chillingham Solar LLC
352 MWAgreement signed Bell, TXERCOT Aug 2020target 2026
Solar project GEN-2020-084, Burt County
Solar
350 MWAgreement signed Burt, NESPP Apr 2020target 2030
Cantaloupe Solar
Solar · Saragosa Del Sol Energy, LLC
307 MWAgreement signed Reeves, TXERCOT Dec 2020target 2028
Pleasant Grove Solar
Solar · Deriva Energy Solar, LLC
300 MWIn study Mchenry, ILPJM Mar 2020target 2023
Butterfly Meadows
Solar · Butterfly Meadows Solar Project, LLC
300 MWIn study Van Wert, OHPJM Sep 2020target 2024
Solar project J1710, Lee County
Solar
300 MWIn study Lee, ARMISO Jun 2020target 2026
Mammoth South Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Mammoth Central Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Solar project J1712, Perry County
Solar
300 MWIn study Perry, ILMISO Jun 2020target 2025
Solar project J1836, Callaway County
Solar
300 MWIn study Callaway, MOMISO Jun 2020target 2025
Dawson Solar
Solar · Deriva Energy Solar, LLC
300 MWIn study Mclean, ILPJM Sep 2020target 2024
Mammoth Central II Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Sep 2020target 2028
Burr Oak Solar
Solar · Leeward Renewable Energy Development, LLC
300 MWIn study Dekalb, ILPJM Aug 2020target 2023
South Dixon Solar
Solar · Deriva Energy Solar, LLC
300 MWIn study Lee, ILPJM Mar 2020target 2022
Solar project GEN-2020-054, Bowie County
Solar
298 MWAgreement signed Bowie, TXSPP Apr 2020target 2027
Sandow Solar
Solar · Sandow Lakes Ranch Solar I, LLC
287 MWIn study Milam, TXERCOT Sep 2020target 2028
Beacon Solar
Solar · Beacon Solar, LLC
260 MWIn study Rock Island, ILPJM Sep 2020target 2023
Mayapple Solar
Solar
260 MWAgreement signed Pulaski, INPJM Sep 2020target 2027
Sierra Madre Solar
Solar · Sierra Madre Solar LLC
255 MWIn study Zapata, TXERCOT Jan 2020target 2027
Gipper Solar Farm
Solar · Gipper Solar Farm, LLC
255 MWIn study Whiteside, ILPJM Oct 2020target 2023
Pandora Solar
Solar
252 MWPaused / redesign Wilson, TXERCOT Jan 2020
Tanglewood Solar
Solar · Brazoria Solar, LLC
251 MWAgreement signed Brazoria, TXERCOT Jul 2020target 2026
Samson Solar 3
Solar · Samson Solar Energy III LLC
250 MWAgreement signed Lamar, TXERCOT Jan 2020target 2026
Solar project J1573, Portage County
Solar
250 MWAgreement signed Portage, WIMISO Jun 2020target 2026
Goldfinch Solar
Solar · Goldfinch Solar, LLC
250 MWAgreement signed Mason, KYPJM Feb 2020target 2030
Solar project GEN-2020-094, Otoe County
Solar
250 MWAgreement signed Otoe, NESPP Apr 2020target 2030
Solar project J1614, Muskegon County
Solar
250 MWAgreement signed Muskegon, MIMISO Jun 2020target 2025
Solar project J1840, Dewitt County
Solar
250 MWIn study Dewitt, ILMISO Jun 2020target 2023
Iguala Solar
Solar
250 MWPaused / redesign Victoria, TXERCOT Oct 2020target 2025
Lavaca Bay Solar
Solar · Lavaca Bay Solar Project, LLC
244 MWAgreement signed Matagorda, TXERCOT Sep 2020target 2026
Pluto Solar
Solar
228 MWPaused / redesign Webb, TXERCOT Jun 2020target 2028
Solar project J1502, Juneau County
Solar
225 MWAgreement signed Juneau, WIMISO Jun 2020target 2026
Solar project IC-908, Turner County
Solar
220 MWPaused / redesign Turner, GASoutheast Oct 2020target 2023
Page 1 of 7

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)