United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTIguala Solar
Iguala Solar is a 250 MW solar request suspended in the ERCOT interconnection queue, in Victoria County, Texas.
Queue statusPaused / redesign
- PlanningQueued Oct 2020 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 23INR0090
- Grid region
- ERCOT (Texas)
- Location
- Victoria County, Texas
- Technology
- Solar: 250 MW
- Total requested
- 250 MW
- Queue status
- Suspended
- Entered queue
- 6 October 2020
- Proposed online date
- December 2025
Location
Marker shows the centre of Victoria County; the queue data does not give exact sites.
Other requests in Victoria County
- Crossroads WindOnshore wind Β· 277 MW Β· agreement signed
- Leopard BESSBattery storage Β· 264 MW Β· agreement signed
- Oriana SolarSolar + storage Β· 181 MW Β· agreement signed
- Two Brothers ESSBattery storage Β· 152 MW Β· agreement signed
- Brizo BESSBattery storage Β· 141 MW Β· agreement signed
- Oriana BESSSolar + storage Β· 60.3 MW Β· agreement signed
- HyFuels Green Lake SolarSolar Β· 347 MW Β· in study
- HyFuels Calhoun SolarSolar Β· 302 MW Β· in study
- Marcos Solar SLFSolar + storage Β· 216 MW Β· in study
- Oak Belt StorageSolar + storage Β· 207 MW Β· in study
- Calico BESSBattery storage Β· 205 MW Β· in study
- Arpeggio BESSBattery storage Β· 201 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem