United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTPluto Solar
Pluto Solar is a 228 MW solar request suspended in the ERCOT interconnection queue, in Webb County, Texas.
Queue statusPaused / redesign
- PlanningQueued Jun 2020 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 22INR0362
- Grid region
- ERCOT (Texas)
- Location
- Webb County, Texas
- Technology
- Solar: 228 MW
- Total requested
- 228 MW
- Queue status
- Suspended
- Entered queue
- 25 June 2020
- Proposed online date
- July 2028
Location
Marker shows the centre of Webb County; the queue data does not give exact sites.
Other requests in Webb County
- SieteOnshore wind Β· 493 MW Β· agreement signed
- Cuchillas SolarSolar + storage Β· 306 MW Β· agreement signed
- Corazon Solar Phase IISolar + storage Β· 204 MW Β· agreement signed
- Corvus SolarSolar Β· 202 MW Β· agreement signed
- Seven Flags BESSBattery storage Β· 103 MW Β· agreement signed
- Cedro Hill Wind RepowerOnshore wind Β· 9.9 MW Β· agreement signed
- Torrecillas BESSBattery storage Β· 9.9 MW Β· agreement signed
- Outpost StorageSolar + storage Β· 508 MW Β· in study
- Siete WindOnshore wind Β· 493 MW Β· in study
- Cuchillas BESSSolar + storage Β· 307 MW Β· in study
- Cenizo SolarSolar Β· 301 MW Β· in study
- Bendito WindOnshore wind Β· 300 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem