United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Solar withdrawn queue requests in the USA

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,252860.3 GW
Active in queue427.5 GW2,995 requests
Agreement signed108.2 GW781 requests
Withdrawn9,252860.3 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,252 requests ยท page 1 of 186
ProjectCapacityStatusLocationRegionQueuedOnline
Ses Solar Six
Solar
1,400 MWWithdrawn / abandoned San Bernardino, CACAISO Jun 2006target 2013
Solar project G0624, Garfield County
Solar
1,250 MWWithdrawn / abandoned Garfield, WAWest May 2019target 2023
Corner Solar
Solar ยท Shannon Solar LLC
1,222 MWWithdrawn / abandoned Crockett, TXERCOT Jun 2019target 2021
Solar project AF1-236, Tyrrell County
Solar
1,210 MWWithdrawn / abandoned Tyrrell, NCPJM Sep 2019target 2024
Ses Solar Seven
Solar
1,200 MWWithdrawn / abandoned San Bernardino, CACAISO Aug 2006target 2011
Alta 13
Solar
1,150 MWWithdrawn / abandoned San Bernardino, CACAISO May 2008target 2013
Suncrest Imperial Segs
Solar
1,080 MWWithdrawn / abandoned Imperial, CACAISO Mar 2011target 2015
Central Valley I Segs
Solar
1,080 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2015
Heartland Solar-2
Solar
1,045 MWWithdrawn / abandoned Fresno, CACAISO May 2016target 2020
Heartland Solar
Solar
1,045 MWWithdrawn / abandoned Fresno, CACAISO May 2016target 2020
Paluxy Solar
Solar ยท S&S Renewables LLC
1,029 MWWithdrawn / abandoned ERCOT Jan 2023target 2027
Desert Ruby PV
Solar
1,000 MWWithdrawn / abandoned San Bernardino, CACAISO Jun 2007target 2013
Kern Solar Ranch (Fka California Solar Ranch)
Solar
1,000 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2018
Solar project GEN-2022-036, Lamb County
Solar
1,000 MWWithdrawn / abandoned Lamb, TXSPP Jun 20222025
Wildcat Quartszite
Solar
1,000 MWWithdrawn / abandoned Yuma, AZCAISO Jul 2010target 2015
Solar project 104, Apache County
Solar
1,000 MWWithdrawn / abandoned Apache, AZWest Nov 2021target 2026
Solar project Company 157, Lincoln County
Solar
1,000 MWWithdrawn / abandoned Lincoln, NVWest Mar 2018target 2020
Solar project C3-052, Carbon County
Solar
1,000 MWWithdrawn / abandoned Carbon, WYWest May 2023target 2026
Desert Opal III PV
Solar
1,000 MWWithdrawn / abandoned San Bernardino, CACAISO Jun 2007target 2016
Solar project G0583, Jefferson County
Solar
1,000 MWWithdrawn / abandoned Jefferson, ORWest Mar 2018target 2021
Coyote Springs
Solar
960 MWWithdrawn / abandoned Lincoln, NVCAISO Jul 2009target 2015
Jeep Wrangler
Solar
960 MWWithdrawn / abandoned Yuma, AZCAISO Jul 2009target 2014
Cadiz West
Solar
900 MWWithdrawn / abandoned San Bernardino, CACAISO May 2008target 2015
La Posa
Solar
900 MWWithdrawn / abandoned La Paz, AZCAISO May 2008target 2015
Az Bighorn
Solar
900 MWWithdrawn / abandoned Maricopa, AZCAISO May 2008target 2015
Solar project Q57, Maricopa County
Solar
900 MWWithdrawn / abandoned Maricopa, AZWest Dec 2008target 2013
Solar project Q044a., Yuma County
Solar
900 MWWithdrawn / abandoned Yuma, AZWest May 2008target 2012
Ranegras Eagletail
Solar
900 MWWithdrawn / abandoned La Paz, AZCAISO May 2008target 2014
Solar project GEN-2023-095, Quay County
Solar
850 MWWithdrawn / abandoned Quay, NMSPP Oct 2023target 2028
K Road Calico Solar LLC (KRCS) (Fka Calico Solar 1; Ses Solar One)
Solar
850 MWWithdrawn / abandoned San Bernardino, CACAISO May 2005target 2013
Solar project GEN-2022-052, Bossier Parish County
Solar
850 MWWithdrawn / abandoned Bossier Parish, LASPP Jun 20222025
Clearwater Solar Generating Station
Solar
840 MWWithdrawn / abandoned Los Angeles, CACAISO Jun 2008target 2014
WSP 3
Solar
800 MWWithdrawn / abandoned Kings, CACAISO Mar 2011target 2018
Solar project Q39, Maricopa County
Solar
800 MWWithdrawn / abandoned Maricopa, AZWest Dec 2007target 2015
Solar project 2021-G4
Solar
765 MWWithdrawn / abandoned West Oct 2021target 2023
Trilobite Solar Project
Solar
750 MWWithdrawn / abandoned San Bernardino, CACAISO Dec 2007target 2012
Palomas Solar
Solar
750 MWWithdrawn / abandoned Yuma, AZCAISO Jul 2009target 2015
Palo Verde Mesa (Fka Brightsource Midpoint Solar)
Solar
750 MWWithdrawn / abandoned Riverside, CACAISO Jul 2010target 2015
California City Solar
Solar
732 MWWithdrawn / abandoned Kern, CACAISO May 2016target 2020
Gigantes Solar
Solar
730 MWWithdrawn / abandoned Imperial, CACAISO May 2016target 2020
Copper Rays
Solar
722 MWWithdrawn / abandoned Nye, NVCAISO May 2016target 2021
Tehuacana Creek Solar-Alt POI
Solar ยท Tehuacana Creek Solar LLC
715 MWWithdrawn / abandoned Freestone, TXERCOT Oct 2022target 2025
Hollow Branch Creek Solar SLF
Solar ยท Hollow Branch Creek Solar LLC
712 MWWithdrawn / abandoned Leon, TXERCOT Dec 2021target 2025
PV-49
Solar
700 MWWithdrawn / abandoned Kern, CACAISO May 2008target 2011
Solar project 66858, Columbus County
Solar ยท Masked
700 MWWithdrawn / abandoned Columbus, NCSoutheast Feb 2020
CVH Power II
Solar
700 MWWithdrawn / abandoned Maricopa, AZCAISO Mar 2011target 2014
Solar project Q17, Maricopa County
Solar
700 MWWithdrawn / abandoned Maricopa, AZWest Apr 2011target 2014
Solar project GEN-2022-086, Finney County
Solar
700 MWWithdrawn / abandoned Finney, KSSPP Nov 2022target 2027
PV-47
Solar
700 MWWithdrawn / abandoned Kern, CACAISO May 2008target 2011
PV-48
Solar
700 MWWithdrawn / abandoned Kern, CACAISO May 2008target 2013
Page 1 of 186

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)