SOLAR Β· CAISOAz Bighorn
Az Bighorn is a 900 MW solar request withdrawn in the CAISO interconnection queue, in Maricopa County, Arizona, connecting to SCE.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2008 (completed)
- Withdrawn / abandonedDec 2009 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 389
- Grid region
- CAISO (California)
- Utility / transmission owner
- SCE
- Connection point (POI)
- Devers-Palo Verde Line 500 kV line
- Location
- Maricopa County, Arizona
- Technology
- Solar: 900 MW
- Total requested
- 900 MW
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 29 May 2008
- Proposed online date
- May 2015
- Withdrawn
- December 2009
Location
Marker shows the centre of Maricopa County; the queue data does not give exact sites.
Other requests in Maricopa County
- Battery storage project Q269, Maricopa CountyBattery storage Β· 450 MW Β· under construction
- Solar + storage project Q332, Maricopa CountySolar + storage Β· 350 MW Β· under construction
- Battery storage project Q357, Maricopa CountyBattery storage Β· 150 MW Β· under construction
- Battery storage project Q268, Maricopa CountyBattery storage Β· 75.0 MW Β· under construction
- Solar + storage project Q360, Maricopa CountySolar + storage Β· 550 MW Β· agreement signed
- Battery storage project Q280, Maricopa CountyBattery storage Β· 300 MW Β· agreement signed
- Battery storage project Q375, Maricopa CountyBattery storage Β· 300 MW Β· agreement signed
- Battery storage project Q299, Maricopa CountyBattery storage Β· 150 MW Β· agreement signed
- Saddle Mountain SolarSolar Β· 125 MW Β· agreement signed
- Battery storage project Q358, Maricopa CountyBattery storage Β· 100 MW Β· agreement signed
- StanleySolar + storage Β· 2,071 MW Β· in study
- Battery storage project Q2405, Maricopa CountyBattery storage Β· 1,020 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem