Battery storage project Q269, Maricopa County

Battery storage project Q269, Maricopa County is a 450 MW battery storage request under construction in the West interconnection queue, in Maricopa County, Arizona, connecting to Arizona Public Service.

Queue statusUnder construction
  1. PlanningQueued Mar 2018 (completed)
  2. Consented (completed)
  3. Construction (current stage)
  4. OperatingTarget Dec 2022 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
Q269
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Delaney 500kV SY
Location
Maricopa County, Arizona
Technology
Battery: 450 MW
Total requested
450 MW
Service type
Network resource (NRIS)
Study phase
In Construction
Queue status
Active
Entered queue
29 March 2018
Proposed online date
December 2022

Location

Marker shows the centre of Maricopa County; the queue data does not give exact sites.