SOLAR Β· WESTSolar project G0583, Jefferson County
Solar project G0583, Jefferson County is a 1,000 MW solar request withdrawn in the West interconnection queue, in Jefferson County, Oregon.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2018 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G0583
- Grid region
- West (non-ISO utilities)
- Connection point (POI)
- Ashe - Marion 500 kV transmission line
- Location
- Jefferson County, Oregon
- Technology
- Solar: 1,000 MW
- Total requested
- 1,000 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 2 March 2018
- Proposed online date
- March 2021
Location
Marker shows the centre of Jefferson County; the queue data does not give exact sites.
Other requests in Jefferson County
- Solar + storage project 21-098, Jefferson CountySolar + storage Β· 250 MW Β· agreement signed
- Solar project QF19-081, Jefferson CountySolar Β· 53.0 MW Β· agreement signed
- Solar + storage project G0758, Jefferson CountySolar + storage Β· 1,365 MW Β· in study
- Solar + storage project 23-233, Jefferson CountySolar + storage Β· 800 MW Β· in study
- Solar + storage project 23-234, Jefferson CountySolar + storage Β· 800 MW Β· in study
- Other project 23-229, Jefferson CountyOther Β· 750 MW Β· in study
- Onshore wind project 23-226, Jefferson CountyOnshore wind Β· 250 MW Β· in study
- Onshore wind project 23-227, Jefferson CountyOnshore wind Β· 250 MW Β· in study
- Onshore wind project 23-228, Jefferson CountyOnshore wind Β· 250 MW Β· in study
- Onshore wind project 23-231, Jefferson CountyOnshore wind Β· 250 MW Β· in study
- Solar + storage project G0839, Jefferson CountySolar + storage Β· 230 MW Β· in study
- Solar + storage project G0838, Jefferson CountySolar + storage Β· 230 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem