United States β€Ί Grid β€Ί Interconnection queues β€Ί Arizona

SOLAR Β· WEST

Solar project 104, Apache County

Solar project 104, Apache County is a 1,000 MW solar request withdrawn in the West interconnection queue, in Apache County, Arizona, connecting to Tucson Electric Power Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
104
Grid region
West (non-ISO utilities)
Utility / transmission owner
Tucson Electric Power Company
Connection point (POI)
Springerville-Mckinley 345kV Transmission Line
Location
Apache County, Arizona
Technology
Solar: 1,000 MW
Total requested
1,000 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
15 November 2021
Proposed online date
March 2026

Location

Marker shows the centre of Apache County; the queue data does not give exact sites.

Power plants in Arizona Β· Transmission lines in Arizona

Other requests in Apache County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem