United States βΊ Grid βΊ Interconnection queues βΊ Louisiana
SOLAR Β· SPPSolar project GEN-2022-052, Bossier Parish County
Solar project GEN-2022-052, Bossier Parish County is a 850 MW solar request withdrawn in the SPP interconnection queue, in Bossier Parish County, Louisiana, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2022 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingDec 2025 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2022-052
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Longwood to Sarepta 345 kV Line Tap
- Location
- Bossier Parish County, Louisiana
- Technology
- Solar: 850 MW
- Total requested
- 850 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 23 June 2022
- Proposed online date
- December 2025
- Came online
- December 2025
- Withdrawn
- November 2023
Location
Marker shows the centre of Bossier Parish County; the queue data does not give exact sites.
Power plants in Louisiana Β· Transmission lines in Louisiana
Other requests in Bossier Parish County
- Gas project GEN-2024-379, Bossier Parish CountyGas Β· 1,350 MW Β· in study
- Battery storage project GEN-2024-177, Bossier Parish CountyBattery storage Β· 199 MW Β· in study
- Solar + storage project GEN-2023-230, Bossier Parish CountySolar + storage Β· 150 MW Β· in study
- Battery storage project GEN-2022-051, Bossier Parish CountyBattery storage Β· 325 MW Β· withdrawn
- Solar + storage project GEN-2021-104, Bossier Parish CountySolar + storage Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem