United States › Grid › Interconnection queues › Louisiana

BATTERY STORAGE · SPP

Battery storage project GEN-2024-177, Bossier Parish County

Battery storage project GEN-2024-177, Bossier Parish County is a 199 MW battery storage request in interconnection study in the SPP interconnection queue, in Bossier Parish County, Louisiana, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-177
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Red Point 138 kV Substation
Location
Bossier Parish County, Louisiana
Technology
Battery: 199 MW
Total requested
199 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
January 2029

Location

Marker shows the centre of Bossier Parish County; the queue data does not give exact sites.

Power plants in Louisiana · Transmission lines in Louisiana

Other requests in Bossier Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem