United States โบ Grid โบ Interconnection queues โบ Wisconsin
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in Wisconsin
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Other project G166, Sheboygan County Other |
2,400 MW | Withdrawn / abandoned |
| Other project G167, Kenosha County Other |
1,200 MW | Withdrawn / abandoned |
| Gas project J435, Eau Claire County Gas |
1,185 MW | Withdrawn / abandoned |
| Other project G052, Sheboygan County Other |
1,000 MW | Withdrawn / abandoned |
| Gas project H004, Eau Claire County Gas |
860 MW | Withdrawn / abandoned |
| Gas project J336, Calumet County Gas |
845 MW | Withdrawn / abandoned |
| Gas project J338, Winnebago County Gas |
845 MW | Withdrawn / abandoned |
| Gas project J560, Douglas County Gas |
835 MW | Withdrawn / abandoned |
| Gas project G068, Racine County Gas |
800 MW | Withdrawn / abandoned |
| Other project G062, Wood County Other |
755 MW | Withdrawn / abandoned |
| Other project G048, Fond Du Lac County Other |
725 MW | Withdrawn / abandoned |
| Gas project J3330, Kenosha County Gas |
705 MW | Withdrawn / abandoned |
| Gas project J248, Outagamie County Gas |
675 MW | Withdrawn / abandoned |
| Gas project G524, Brown County Gas |
600 MW | Withdrawn / abandoned |
| Other project G036, Wood County Other |
600 MW | Withdrawn / abandoned |
| Other project G086, Brown County Other |
600 MW | Withdrawn / abandoned |
| Gas project G254, Portage County Gas |
590 MW | Withdrawn / abandoned |
| Gas project J294, Brown County Gas |
588 MW | Withdrawn / abandoned |
| Gas project J383, Manitowoc County Gas |
571 MW | Withdrawn / abandoned |
| Gas project J337, Winnebago County Gas |
551 MW | Withdrawn / abandoned |
| Gas project J335, Calumet County Gas |
551 MW | Withdrawn / abandoned |
| Coal project G528, Columbia County Coal |
550 MW | Withdrawn / abandoned |
| Coal project G522, Portage County Coal |
550 MW | Withdrawn / abandoned |
| Gas project J389, Rock County Gas |
550 MW | Withdrawn / abandoned |
| Coal project G523, Marathon County Coal |
550 MW | Withdrawn / abandoned |
| Other project G102, Calumet County Other |
530 MW | Withdrawn / abandoned |
| Other project G100, Winnebago County Other |
530 MW | Withdrawn / abandoned |
| Other project G152, Calumet County Other |
530 MW | Withdrawn / abandoned |
| Other project G101, Outagamie County Other |
530 MW | Withdrawn / abandoned |
| Coal project G295, Portage County Coal |
525 MW | Withdrawn / abandoned |
| Other project G131, Brown County Other |
500 MW | Withdrawn / abandoned |
| Gas project J293, Outagamie County Gas |
496 MW | Withdrawn / abandoned |
| Gas project J4020, Kenosha County Gas |
481 MW | Withdrawn / abandoned |
| Solar project J1010, Kenosha County Solar |
400 MW | Withdrawn / abandoned |
| Solar project J1009, Kenosha County Solar |
400 MW | Withdrawn / abandoned |
| Coal project G293, Buffalo County Coal |
400 MW | Withdrawn / abandoned |
| Solar project J1011, Kenosha County Solar |
400 MW | Withdrawn / abandoned |
| Onshore wind project G987, Brown County Onshore wind |
400 MW | Withdrawn / abandoned |
| Other project G138, Walworth County Other |
352 MW | Withdrawn / abandoned |
| Other project G054, Waukesha County Other |
350 MW | Withdrawn / abandoned |
| Other project G045, Rock County Other |
330 MW | Withdrawn / abandoned |
| Gas project G117, Douglas County Gas |
324 MW | Withdrawn / abandoned |
| Gas project J1838, Dane County Gas |
320 MW | Withdrawn / abandoned |
| Other project G050, Portage County Other |
320 MW | Withdrawn / abandoned |
| Battery storage project J4171, Racine County Battery storage |
300 MW | Withdrawn / abandoned |
| Onshore wind project J1085, Marathon County Onshore wind |
300 MW | Withdrawn / abandoned |
| Gas project J129, Polk County Gas |
300 MW | Withdrawn / abandoned |
| Solar project J1053, Jefferson County Solar |
300 MW | Withdrawn / abandoned |
| Solar project J1753, Green County Solar |
300 MW | Withdrawn / abandoned |
| Solar project J2417, Trempealeau County Solar |
300 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)