πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

BATTERY STORAGE Β· MISO

Battery storage project J4171, Racine County

Battery storage project J4171, Racine County is a 300 MW battery storage request withdrawn in the MISO interconnection queue, in Racine County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2025 (completed)
  2. Withdrawn / abandonedJan 2026 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J4171
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMERICAN TRANSMISSION COMPANY
Connection point (POI)
138 kV Jupiter Substation (#50167)
Location
Racine County, Wisconsin
Technology
Battery: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
7 October 2025
Proposed online date
April 2029
Withdrawn
January 2026

Location

Marker shows the centre of Racine County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Racine County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem