United States βΊ Grid βΊ Interconnection queues βΊ Wisconsin
GAS Β· MISOGas project J389, Rock County
Gas project J389, Rock County is a 550 MW gas request withdrawn in the MISO interconnection queue, in Rock County, Wisconsin.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2014 (completed)
- Withdrawn / abandonedJun 2015 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J389
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Unknown
- Location
- Rock County, Wisconsin
- Technology
- Gas: 550 MW
- Total requested
- 550 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 15 September 2014
- Withdrawn
- June 2015
Location
Marker shows the centre of Rock County; the queue data does not give exact sites.
Power plants in Wisconsin Β· Transmission lines in Wisconsin
Other requests in Rock County
- Solar project J1460, Rock CountySolar Β· 200 MW Β· under construction
- Solar project J1377, Rock CountySolar Β· 98.6 MW Β· agreement signed
- Gas project J2947, Rock CountyGas Β· 205 MW Β· in study
- Battery storage project J3162, Rock CountyBattery storage Β· 100 MW Β· in study
- Gas project J3156, Rock CountyGas Β· 100 MW Β· in study
- Solar project J4097, Rock CountySolar Β· 71.5 MW Β· in study
- Surplus; J1304Other Β· 33.0 MW Β· in study
- Surplus; J1188Other Β· 25.0 MW Β· in study
- Gas project J390, Rock CountyGas Β· 711 MW Β· built
- Gas project G035, Rock CountyGas Β· 505 MW Β· built
- Solar project J850, Rock CountySolar Β· 250 MW Β· built
- Gas project G072, Rock CountyGas Β· 150 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem