Gas project H004, Eau Claire County

Gas project H004, Eau Claire County is a 860 MW gas request withdrawn in the MISO interconnection queue, in Eau Claire County, Wisconsin.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2008 (completed)
  2. Withdrawn / abandonedMay 2009 (project stopped here)
  3. ConsentedMay 2009 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
H004
Grid region
MISO (Midcontinent)
Connection point (POI)
Eau Claire 345 kV Substation
Location
Eau Claire County, Wisconsin
Technology
Gas: 860 MW
Total requested
860 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
14 April 2008
Agreement signed
14 May 2009
Proposed online date
December 2009
Withdrawn
May 2009

Location

Marker shows the centre of Eau Claire County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Eau Claire County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem