United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

GAS Β· MISO

Gas project J560, Douglas County

Gas project J560, Douglas County is a 835 MW gas request withdrawn in the MISO interconnection queue, in Douglas County, Wisconsin.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedApr 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J560
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Douglas County, Wisconsin
Technology
Gas: 835 MW
Total requested
835 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
4 May 2016
Proposed online date
January 2022
Withdrawn
April 2017

Location

Marker shows the centre of Douglas County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Douglas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem