United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

GAS Β· MISO

Gas project J383, Manitowoc County

Gas project J383, Manitowoc County is a 571 MW gas request withdrawn in the MISO interconnection queue, in Manitowoc County, Wisconsin.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2014 (completed)
  2. Withdrawn / abandonedMar 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J383
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Manitowoc County, Wisconsin
Technology
Gas: 571 MW
Total requested
571 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
18 August 2014
Proposed online date
May 2019
Withdrawn
March 2016

Location

Marker shows the centre of Manitowoc County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Manitowoc County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem