BATTERY STORAGE Β· MISO

Battery storage project J2218, Manitowoc County

Battery storage project J2218, Manitowoc County is a 150 MW battery storage request withdrawn in the MISO interconnection queue, in Manitowoc County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedOct 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2218
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMERICAN TRANSMISSION COMPANY
Connection point (POI)
SHOTO
Location
Manitowoc County, Wisconsin
Technology
Battery: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: Re-Study; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
13 August 2021
Proposed online date
September 2024
Withdrawn
October 2024

Location

Marker shows the centre of Manitowoc County; the queue data does not give exact sites.