OCTARY USA ยท INTERCONNECTION QUEUES

Completed queue projects in Wisconsin

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown637,946 MW
Active in queue26.6 GW117 requests
Agreement signed3,635 MW26 requests
Withdrawn24049.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

63 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Coal project G051, Milwaukee County
Coal
1,300 MWOperating Milwaukee, WIMISO Aug 20002003
Gas project J390, Rock County
Gas
711 MWOperating Rock, WIMISO Sep 20142017
Gas project G044, Outagamie County
Gas
600 MWOperating Outagamie, WIMISO Jun 2000
Coal project G144, Marathon County
Coal
550 MWOperating Marathon, WIMISO Oct 20012004
Gas project G035, Rock County
Gas
505 MWOperating Rock, WIMISO Apr 20002003
Onshore wind project G103, Sheboygan County
Onshore wind
370 MWOperating Sheboygan, WIMISO Jun 20012004
Solar project J850, Rock County
Solar
250 MWOperating Rock, WIMISO Jun 20172022
Solar project J947, Grant County
Solar
200 MWOperating Grant, WIMISO Jun 20172023
Gas project G093, Ozaukee County
Gas
200 MWOperating Ozaukee, WIMISO Apr 20012004
Onshore wind project G368, Dodge County
Onshore wind
200 MWOperating Dodge, WIMISO Oct 20032007
Solar project J870, Grant County
Solar
200 MWOperating Grant, WIMISO Jun 20172020
Gas project G072, Rock County
Gas
150 MWOperating Rock, WIMISO Jan 20012009
Onshore wind project H012, Columbia County
Onshore wind
150 MWOperating Columbia, WIMISO Apr 20082011
Solar project J1153, Sheboygan County
Solar
150 MWOperating Sheboygan, WIMISO Mar 20182022
Solar project J886, Manitowoc County
Solar
150 MWOperating Manitowoc, WIMISO Jun 20172020
Gas project G096, Dane County
Gas
105 MWOperating Dane, WIMISO Jun 20012002
Onshore wind project G706, Columbia County
Onshore wind
99.0 MWOperating Columbia, WIMISO Nov 20062008
Solar project J1002, Waushara County
Solar
99.0 MWOperating Waushara, WIMISO Mar 20182023
Solar project J505, Manitowoc County
Solar
99.0 MWOperating Manitowoc, WIMISO Nov 20152021
Onshore wind project J652, Lafayette County
Onshore wind
98.0 MWOperating Lafayette, WIMISO Jul 20162017
Onshore wind project G507b, Fond Du Lac County
Onshore wind
98.0 MWOperating Fond Du Lac, WIMISO Mar 20062008
Onshore wind project J395, Lafayette County
Onshore wind
98.0 MWOperating Lafayette, WIMISO Sep 20142015
Gas project G510, Ozaukee County
Gas
90.0 MWOperating Ozaukee, WIMISO Mar 20052005
Coal project G111, Brown County
Coal
85.0 MWOperating Brown, WIMISO Aug 20012011
Onshore wind project G353, Fond Du Lac County
Onshore wind
80.0 MWOperating Fond Du Lac, WIMISO Jul 20032007
Onshore wind project G354, Fond Du Lac County
Onshore wind
80.0 MWOperating Fond Du Lac, WIMISO Jul 20032009
Onshore wind project G507, Fond Du Lac County
Onshore wind
68.0 MWOperating Fond Du Lac, WIMISO Mar 20052005
Solar project J1304, Rock County
Solar
65.0 MWOperating Rock, WIMISO Apr 20192023
Gas project G225, Outagamie County
Gas
60.0 MWOperating Outagamie, WIMISO May 20022004
Gas project G588, Wood County
Gas
59.7 MWOperating Wood, WIMISO Jan 20062007
Gas project J142, Wood County
Gas
59.7 MWOperating Wood, WIMISO Jun 2010target 2011
Gas project G240, Manitowoc County
Gas
55.0 MWOperating Manitowoc, WIMISO Jul 20022009
Onshore wind project G338, Dodge County
Onshore wind
54.0 MWOperating Dodge, WIMISO Apr 20032003
Nuclear project G834, Manitowoc County
Nuclear
53.0 MWOperating Manitowoc, WIMISO Aug 20072008
Nuclear project G833, Manitowoc County
Nuclear
53.0 MWOperating Manitowoc, WIMISO Aug 20072009
Gas project G074, Outagamie County
Gas
50.0 MWOperating Outagamie, WIMISO Jan 20012005
Solar project J1188, Rock County
Solar
50.0 MWOperating Rock, WIMISO Mar 20182022
Solar project J864, Richland County
Solar
50.0 MWOperating Richland, WIMISO Jun 20172022
Solar project J1003, Dodge County
Solar
50.0 MWOperating Dodge, WIMISO Mar 20182023
Solar project J1000, Grant County
Solar
50.0 MWOperating Grant, WIMISO Mar 20182023
Solar project J1305, Green County
Solar
49.9 MWOperating Green, WIMISO Apr 20192023
Gas project J382, Dane County
Gas
48.3 MWOperating Dane, WIMISO Jul 20142020
Gas project J831, Ozaukee County
Gas
48.0 MWOperating Ozaukee, WIMISO Jun 20172019
Gas project G160, Dane County
Gas
45.0 MWOperating Dane, WIMISO Nov 20012003
Gas project J174, Jefferson County
Gas
43.8 MWOperating Jefferson, WIMISO Nov 20102011
Nuclear project G165, Kewaunee County
Nuclear
38.0 MWOperating Kewaunee, WIMISO Dec 20012007
Gas project J760, Rock County
Gas
30.0 MWOperating Rock, WIMISO Nov 20162019
Gas project G550, Jefferson County
Gas
24.0 MWOperating Jefferson, WIMISO Sep 20052006
Gas project G148, Juneau County
Gas
20.0 MWOperating Juneau, WIMISO Nov 20012003
Other project G327, Marinette County
Other
19.0 MWOperating Marinette, WIMISO Mar 20032003
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)