United States › Grid › Interconnection queues › Wisconsin

SOLAR · MISO

Solar project J864, Richland County

Solar project J864, Richland County is a 50.0 MW solar request built and operating in the MISO interconnection queue, in Richland County, Wisconsin, connecting to American Transmission Co..

Queue statusOperating
  1. PlanningQueued Jun 2017 (completed)
  2. ConsentedApr 2020 (completed)
  3. Construction (completed)
  4. OperatingSep 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J864
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Lone Rock 69kV Substation
Location
Richland County, Wisconsin
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: In Service
Queue status
Operational
Entered queue
16 June 2017
Agreement signed
27 April 2020
Proposed online date
September 2022
Came online
September 2022

Location

Marker shows the centre of Richland County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem