United States › Grid › Interconnection queues › Wisconsin
GAS · MISOGas project G044, Outagamie County
Gas project G044, Outagamie County is a 600 MW gas request built and operating in the MISO interconnection queue, in Outagamie County, Wisconsin.
Request details
- Queue ID
- G044
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Point Beach - North Appleton 345kV
- Location
- Outagamie County, Wisconsin
- Technology
- Gas: 600 MW
- Total requested
- 600 MW
- Study phase
- Network Upgrade
- Queue status
- Operational
- Entered queue
- 28 June 2000
Location
Marker shows the centre of Outagamie County; the queue data does not give exact sites.
Other requests in Outagamie County
- Battery storage project J2326, Outagamie CountyBattery storage · 150 MW · in study
- Gas project G225, Outagamie CountyGas · 60.0 MW · built
- Gas project G074, Outagamie CountyGas · 50.0 MW · built
- Gas project J248, Outagamie CountyGas · 675 MW · withdrawn
- Other project G101, Outagamie CountyOther · 530 MW · withdrawn
- Gas project J293, Outagamie CountyGas · 496 MW · withdrawn
- Solar project J2148, Outagamie CountySolar · 200 MW · withdrawn
- Solar project J1567, Outagamie CountySolar · 150 MW · withdrawn
- Battery storage project J2074, Outagamie CountyBattery storage · 100 MW · withdrawn
- Gas project G231, Outagamie CountyGas · 60.0 MW · withdrawn
- Gas project G224, Outagamie CountyGas · 60.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem