πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

SOLAR Β· MISO

Solar project J2148, Outagamie County

Solar project J2148, Outagamie County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Outagamie County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2021 (completed)
  2. Withdrawn / abandonedNov 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2148
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMERICAN TRANSMISSION COMPANY
Connection point (POI)
Werner West 138 kV
Location
Outagamie County, Wisconsin
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: Re-Study; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
18 October 2021
Proposed online date
December 2028
Withdrawn
November 2025

Location

Marker shows the centre of Outagamie County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Outagamie County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem