United States › Grid › Interconnection queues › Wisconsin
BATTERY STORAGE · MISOBattery storage project J2326, Outagamie County
Battery storage project J2326, Outagamie County is a 150 MW battery storage request in interconnection study in the MISO interconnection queue, in Outagamie County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2326
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- Werner West
- Location
- Outagamie County, Wisconsin
- Technology
- Battery: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 13 September 2022
- Proposed online date
- October 2025
Location
Marker shows the centre of Outagamie County; the queue data does not give exact sites.
Other requests in Outagamie County
- Gas project G044, Outagamie CountyGas · 600 MW · built
- Gas project G225, Outagamie CountyGas · 60.0 MW · built
- Gas project G074, Outagamie CountyGas · 50.0 MW · built
- Gas project J248, Outagamie CountyGas · 675 MW · withdrawn
- Other project G101, Outagamie CountyOther · 530 MW · withdrawn
- Gas project J293, Outagamie CountyGas · 496 MW · withdrawn
- Solar project J2148, Outagamie CountySolar · 200 MW · withdrawn
- Solar project J1567, Outagamie CountySolar · 150 MW · withdrawn
- Battery storage project J2074, Outagamie CountyBattery storage · 100 MW · withdrawn
- Gas project G231, Outagamie CountyGas · 60.0 MW · withdrawn
- Gas project G224, Outagamie CountyGas · 60.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem