United States βΊ Grid βΊ Interconnection queues βΊ Wisconsin
BATTERY STORAGE Β· MISOBattery storage project J2074, Outagamie County
Battery storage project J2074, Outagamie County is a 100 MW battery storage request withdrawn in the MISO interconnection queue, in Outagamie County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2021 (completed)
- Withdrawn / abandonedOct 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2074
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- Werner West 138 kV
- Location
- Outagamie County, Wisconsin
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: Re-Study; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 18 October 2021
- Proposed online date
- September 2024
- Withdrawn
- October 2024
Location
Marker shows the centre of Outagamie County; the queue data does not give exact sites.
Power plants in Wisconsin Β· Transmission lines in Wisconsin
Other requests in Outagamie County
- Battery storage project J2326, Outagamie CountyBattery storage Β· 150 MW Β· in study
- Gas project G044, Outagamie CountyGas Β· 600 MW Β· built
- Gas project G225, Outagamie CountyGas Β· 60.0 MW Β· built
- Gas project G074, Outagamie CountyGas Β· 50.0 MW Β· built
- Gas project J248, Outagamie CountyGas Β· 675 MW Β· withdrawn
- Other project G101, Outagamie CountyOther Β· 530 MW Β· withdrawn
- Gas project J293, Outagamie CountyGas Β· 496 MW Β· withdrawn
- Solar project J2148, Outagamie CountySolar Β· 200 MW Β· withdrawn
- Solar project J1567, Outagamie CountySolar Β· 150 MW Β· withdrawn
- Gas project G231, Outagamie CountyGas Β· 60.0 MW Β· withdrawn
- Gas project G224, Outagamie CountyGas Β· 60.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem