United States › Grid › Interconnection queues › Wisconsin
SOLAR · MISOSolar project J1002, Waushara County
Solar project J1002, Waushara County is a 99.0 MW solar request built and operating in the MISO interconnection queue, in Waushara County, Wisconsin, connecting to American Transmission Co..
Request details
- Queue ID
- J1002
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- American Transmission Co.
- Connection point (POI)
- Wautoma 138kV Switchyard
- Location
- Waushara County, Wisconsin
- Technology
- Solar: 99.0 MW
- Total requested
- 99.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: In Service
- Queue status
- Operational
- Entered queue
- 12 March 2018
- Agreement signed
- 5 May 2021
- Proposed online date
- January 2023
- Came online
- January 2023
Location
Marker shows the centre of Waushara County; the queue data does not give exact sites.
Other requests in Waushara County
- Solar + storage project J2193, Waushara CountySolar + storage · 100 MW · in study
- Solar project J2609, Waushara CountySolar · 80.0 MW · in study
- Surplus; J1002Other · 50.0 MW · in study
- Solar project J668, Waushara CountySolar · 100 MW · withdrawn
- Solar project J2303, Waushara CountySolar · 100 MW · withdrawn
- Solar project J1596, Waushara CountySolar · 100 MW · withdrawn
- Solar project J1719, Waushara CountySolar · 100 MW · withdrawn
- Battery storage project J1739, Waushara CountyBattery storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem