United States βΊ Grid βΊ Interconnection queues βΊ Wisconsin
BATTERY STORAGE Β· MISOBattery storage project J1739, Waushara County
Battery storage project J1739, Waushara County is a 50.0 MW battery storage request withdrawn in the MISO interconnection queue, in Waushara County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandonedFeb 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1739
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- Sand Lake 138kV Substation
- Location
- Waushara County, Wisconsin
- Technology
- Battery: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 24 June 2020
- Proposed online date
- September 2023
- Withdrawn
- February 2021
Location
Marker shows the centre of Waushara County; the queue data does not give exact sites.
Power plants in Wisconsin Β· Transmission lines in Wisconsin
Other requests in Waushara County
- Solar + storage project J2193, Waushara CountySolar + storage Β· 100 MW Β· in study
- Solar project J2609, Waushara CountySolar Β· 80.0 MW Β· in study
- Surplus; J1002Other Β· 50.0 MW Β· in study
- Solar project J1002, Waushara CountySolar Β· 99.0 MW Β· built
- Solar project J668, Waushara CountySolar Β· 100 MW Β· withdrawn
- Solar project J2303, Waushara CountySolar Β· 100 MW Β· withdrawn
- Solar project J1596, Waushara CountySolar Β· 100 MW Β· withdrawn
- Solar project J1719, Waushara CountySolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem