United States › Grid › Interconnection queues › Wisconsin
SOLAR · MISOSolar project J2609, Waushara County
Solar project J2609, Waushara County is a 80.0 MW solar request in interconnection study in the MISO interconnection queue, in Waushara County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2609
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- Sand Lake
- Location
- Waushara County, Wisconsin
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 13 September 2022
- Proposed online date
- September 2026
Location
Marker shows the centre of Waushara County; the queue data does not give exact sites.
Other requests in Waushara County
- Solar + storage project J2193, Waushara CountySolar + storage · 100 MW · in study
- Surplus; J1002Other · 50.0 MW · in study
- Solar project J1002, Waushara CountySolar · 99.0 MW · built
- Solar project J668, Waushara CountySolar · 100 MW · withdrawn
- Solar project J2303, Waushara CountySolar · 100 MW · withdrawn
- Solar project J1596, Waushara CountySolar · 100 MW · withdrawn
- Solar project J1719, Waushara CountySolar · 100 MW · withdrawn
- Battery storage project J1739, Waushara CountyBattery storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem