United States โ€บ Grid โ€บ Interconnection queues โ€บ Massachusetts

OCTARY USA ยท INTERCONNECTION QUEUES

Completed queue projects in Massachusetts

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown604,417 MW
Active in queue11.2 GW35 requests
Agreement signed6,013 MW17 requests
Withdrawn37048.3 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

60 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Northfield Mt. Equipment Replacement
Battery storage
1,180 MWOperating Franklin, MAISO-NE Jun 2007target 2008
Footprint Combined Cycle Unit
Gas
716 MWOperating Essex, MAISO-NE Jan 2012target 2013
Canal 3
Gas
333 MWOperating Barnstable, MAISO-NE Mar 2014target 2019
Bear Swamp Pump Load increase
Battery storage
333 MWOperating Berkshire, MAISO-NE May 2022target 2023
Bear Swamp Pumping Load Increase
Battery storage
333 MWOperating Berkshire, MAISO-NE Nov 2021target 2021
Kendall Revised Reconfiguration Project
Gas
250 MWOperating Middlesex, MAISO-NE Oct 2015target 2016
Medway Peaker - SEMARI
Gas
208 MWOperating Norfolk, MAISO-NE May 2014target 2019
Altresco Increase (winter)
Gas
193 MWOperating Berkshire, MAISO-NE Feb 2011target 2012
Cranberry Point Energy Storage
Battery storage
150 MWOperating Plymouth, MAISO-NE Mar 2018target 2025
Thomas A. Watson Generating Station
Gas
108 MWOperating Norfolk, MAISO-NE Aug 2006target 2009
L'Energia
Gas
74.0 MWOperating Middlesex, MAISO-NE Jul 2007target 2009
Simple Cycle Gas Turbine
Gas
61.9 MWOperating Essex, MAISO-NE Jul 2016target 2024
Cogen DG
Gas
43.0 MWOperating Middlesex, MAISO-NE Oct 2016target 2021
MATEP (Medical Area Total Energy Project)
Gas
42.0 MWOperating Suffolk, MAISO-NE May 2006
Combined Cycle Uprate #2
Gas
30.0 MWOperating Worcester, MAISO-NE Feb 2015target 2018
Brayton Point 3 Uprate( see 243)
Coal
30.0 MWOperating Bristol, MAISO-NE Oct 2007target 2011
Hoosac Wind Project
Onshore wind
28.5 MWOperating Berkshire, MAISO-NE May 2003target 2012
Northfield Mt Upgrade #1
Battery storage
25.0 MWOperating Franklin, MAISO-NE Jan 2007target 2011
Crystal Lake Substation - NG Western MA Area Cluster Study
Solar
24.7 MWOperating Worcester, MAISO-NE Dec 2018target 2020
Dartmouth Power Expansion
Gas
24.0 MWOperating Bristol, MAISO-NE Jan 2007target 2009
Wendell Depot Substation - NG Western MA Area Cluster Study
Solar
15.0 MWOperating Franklin, MAISO-NE Dec 2018target 2021
Berkshire Wind Power Project
Onshore wind
15.0 MWOperating Berkshire, MAISO-NE Oct 2000target 2011
MATEP -3rd CTG
Gas
14.1 MWOperating Suffolk, MAISO-NE Jan 2013target 2017
Gas Turbine Increase
Gas
10.9 MWOperating Essex, MAISO-NE Feb 2013target 2013
Solar with Battery
Solar + storage
10.0 MWOperating Worcester, MAISO-NE Sep 2018target 2021
Harrington Street PV Project (QF)
Solar
9.8 MWOperating Worcester, MAISO-NE Sep 2011target 2016
Litchfield substation - NG Western MA Area Cluster Study
Solar
9.5 MWOperating Worcester, MAISO-NE Mar 2019target 2021
Solar
Solar
9.5 MWOperating Plymouth, MAISO-NE Jan 2018target 2019
N. Oxford Substation - NG Western MA Area Cluster Study
Solar
8.7 MWOperating Worcester, MAISO-NE Dec 2018target 2020
Solar
Solar
8.0 MWOperating Worcester, MAISO-NE Dec 2017target 2020
Salem Harbor Station Increase
Other
8.0 MWOperating Essex, MAISO-NE Dec 2010
Belchertown Substation - NG Western MA Area Cluster Study
Solar
8.0 MWOperating Hampden, MAISO-NE Dec 2018target 2021
Combined Reciprocating, Solar and Battery
Solar + storage
7.8 MWOperating Middlesex, MAISO-NE Aug 2018target 2019
Kendall #3 Back Pressure Steam Turbine
Gas
7.5 MWOperating Middlesex, MAISO-NE May 2010target 2010
Fitchburg Renewable Energy
Other
7.2 MWOperating Worcester, MAISO-NE May 2006target 2007
Solar
Solar
6.0 MWOperating Worcester, MAISO-NE Dec 2017target 2020
Increase to Steam Turbine Capacity Uprate (See QP
Coal
6.0 MWOperating Bristol, MAISO-NE Jan 2008target 2011
Kearsarge Solar with battery
Solar + storage
5.4 MWOperating Norfolk, MAISO-NE Aug 2018target 2021
Syncarpha Blandford Solar plus battery storage
Solar + storage
5.0 MWOperating Berkshire, MAISO-NE Sep 2020target 2021
Mass Power Increase
Gas
5.0 MWOperating Hampden, MAISO-NE Sep 2010target 2011
Holiday Hill Community Wind
Onshore wind
5.0 MWOperating Hampden, MAISO-NE Feb 2015target 2020
Dighton Power Uprate
Gas
5.0 MWOperating Bristol, MAISO-NE Sep 2012target 2013
Solar
Solar
4.9 MWOperating Plymouth, MAISO-NE Aug 2018target 2019
Westminster - NG Western MA Area Cluster Study
Solar
4.9 MWOperating Worcester, MAISO-NE Dec 2018target 2021
ENA Old Falmouth Road PV + Storage
Solar + storage
4.8 MWOperating Barnstable, MAISO-NE Apr 2020target 2024
Wilbraham substation - NG Western MA Area Cluster Study
Solar
4.0 MWOperating Hampden, MAISO-NE Mar 2019target 2020
Chestnut Hill 702 Substation - NG Western MA Area Cluster Study
Solar
3.3 MWOperating Worcester, MAISO-NE Dec 2018target 2020
Five Corners Substation - NG Western MA Area Cluster Study
Solar
3.0 MWOperating Hampshire, MAISO-NE Dec 2018target 2021
Leicester - NG Western MA Area Cluster Study
Solar
2.6 MWOperating Worcester, MAISO-NE Dec 2018target 2021
Bear Swamp Upper Yard substation - NG Western MA Area Cluster Study
Solar
2.5 MWOperating Berkshire, MAISO-NE Mar 2019target 2021
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)