United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in CAISO (California) (2019 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Pinebrook Solar Hybrid Energy Center Solar + storage |
3,074 MW | Withdrawn / abandoned |
| Nimitz 2 Generation Wind + storage |
1,887 MW | Withdrawn / abandoned |
| Nimitz 1 Generation Wind + storage |
1,887 MW | Withdrawn / abandoned |
| Tempest Generation Wind + storage |
1,887 MW | Withdrawn / abandoned |
| Seawolf Generation Wind + storage |
1,887 MW | Withdrawn / abandoned |
| Una Lake Solar Solar + storage |
1,243 MW | Withdrawn / abandoned |
| Las Brisas Offshore Wind Offshore wind |
1,188 MW | Withdrawn / abandoned |
| Solo Solar + storage |
1,037 MW | Withdrawn / abandoned |
| Sunnynook Solar Center Solar + storage |
1,029 MW | Withdrawn / abandoned |
| Oatfield Hybrid Solar Solar + storage |
1,000 MW | Withdrawn / abandoned |
| Yeager Hybrid Solar Solar + storage |
813 MW | Withdrawn / abandoned |
| Bradmoor Solar Solar + storage |
719 MW | Withdrawn / abandoned |
| Bright Star Hybrid Solar + storage |
719 MW | Withdrawn / abandoned |
| Steel City Energy Storage Battery storage |
650 MW | Withdrawn / abandoned |
| Ventus Renewable Energy Center Other |
643 MW | Withdrawn / abandoned |
| Salton Solar Solar + storage |
632 MW | Withdrawn / abandoned |
| Lion Rock Offshore Wind Offshore wind |
627 MW | Withdrawn / abandoned |
| Fort Tejon Solar Solar + storage |
617 MW | Withdrawn / abandoned |
| Bullhead Solar Solar + storage |
600 MW | Withdrawn / abandoned |
| Sloan Energy Center Solar + storage |
578 MW | Withdrawn / abandoned |
| Grand Lake Hybrid Solar Solar + storage |
504 MW | Withdrawn / abandoned |
| SV Energy Storage Facility Battery storage |
500 MW | Withdrawn / abandoned |
| Fokus Renewable Energy Center Other |
472 MW | Withdrawn / abandoned |
| Big Duck Storage Battery storage |
462 MW | Withdrawn / abandoned |
| Ranchero Solar Solar + storage |
450 MW | Withdrawn / abandoned |
| Triumph Solar Solar + storage |
450 MW | Withdrawn / abandoned |
| Trestles Energy Storage Battery storage |
434 MW | Withdrawn / abandoned |
| Boulder Oaks Hybrid Wind + storage |
411 MW | Withdrawn / abandoned |
| Doradus Solar + storage |
406 MW | Withdrawn / abandoned |
| Rigal Solar + storage |
406 MW | Withdrawn / abandoned |
| Ash Tree Hybrid Solar Solar + storage |
406 MW | Withdrawn / abandoned |
| Familia Hybrid Solar Solar + storage |
405 MW | Withdrawn / abandoned |
| Garces Hybrid Solar Solar + storage |
403 MW | Withdrawn / abandoned |
| Agua Amarga Wind Onshore wind |
403 MW | Withdrawn / abandoned |
| DRY Grape Hybrid Solar Solar + storage |
403 MW | Withdrawn / abandoned |
| Yellow Hay Hybrid Solar Solar + storage |
400 MW | Withdrawn / abandoned |
| Draco Solar Solar + storage |
375 MW | Withdrawn / abandoned |
| Peony Solar |
359 MW | Withdrawn / abandoned |
| Journey Storage Battery storage |
355 MW | Withdrawn / abandoned |
| Barrenspring Solar + storage |
308 MW | Withdrawn / abandoned |
| Vestal Valley Solar + storage |
308 MW | Withdrawn / abandoned |
| San Bernardino BESS Battery storage |
308 MW | Withdrawn / abandoned |
| Hinson BESS Battery storage |
308 MW | Withdrawn / abandoned |
| Nikola Norte Solar + storage |
306 MW | Withdrawn / abandoned |
| Tesoster Solar + storage |
306 MW | Withdrawn / abandoned |
| Nikovaster Solar + storage |
306 MW | Withdrawn / abandoned |
| Superba Storage 1 Battery storage |
305 MW | Withdrawn / abandoned |
| Arcturus Solar + storage |
304 MW | Withdrawn / abandoned |
| Sugarloaf Hybrid Solar Solar + storage |
303 MW | Withdrawn / abandoned |
| Rancho 2 Energy Storage Battery storage |
250 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)247 Β· 41.2 GW
- CAISO (California)95 Β· 39.6 GW
- PJM (Mid-Atlantic, Midwest)409 Β· 38.5 GW
- Southeast (non-ISO utilities)199 Β· 37.4 GW
- MISO (Midcontinent)153 Β· 21.3 GW
- ERCOT (Texas)109 Β· 20.7 GW
- NYISO (New York)135 Β· 14.9 GW
- SPP (Southwest Power Pool)57 Β· 6,718 MW
- ISO-NE (New England)69 Β· 6,220 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)