United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in CAISO (California) (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9539.6 GW
Active in queue21.8 GW36 requests
Agreement signed19.4 GW33 requests
Withdrawn9539.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

95 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Pinebrook Solar Hybrid Energy Center
Solar + storage
3,074 MWWithdrawn / abandoned Fresno, CACAISO Apr 2019target 2024
Nimitz 2 Generation
Wind + storage
1,887 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2026
Nimitz 1 Generation
Wind + storage
1,887 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2024
Tempest Generation
Wind + storage
1,887 MWWithdrawn / abandoned Humboldt, CACAISO Apr 2019target 2025
Seawolf Generation
Wind + storage
1,887 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2024
Una Lake Solar
Solar + storage
1,243 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2019target 2022
Las Brisas Offshore Wind
Offshore wind
1,188 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2026
Solo
Solar + storage
1,037 MWWithdrawn / abandoned Riverside, CACAISO Apr 2019target 2022
Sunnynook Solar Center
Solar + storage
1,029 MWWithdrawn / abandoned Riverside, CACAISO Apr 2019target 2026
Oatfield Hybrid Solar
Solar + storage
1,000 MWWithdrawn / abandoned Kings, CACAISO Apr 2019target 2022
Yeager Hybrid Solar
Solar + storage
813 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Bradmoor Solar
Solar + storage
719 MWWithdrawn / abandoned Solano, CACAISO Apr 2019target 2022
Bright Star Hybrid
Solar + storage
719 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2019target 2022
Steel City Energy Storage
Battery storage
650 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2019target 2025
Ventus Renewable Energy Center
Other
643 MWWithdrawn / abandoned Riverside, CACAISO Apr 2019target 2023
Salton Solar
Solar + storage
632 MWWithdrawn / abandoned Imperial, CACAISO Apr 2019target 2023
Lion Rock Offshore Wind
Offshore wind
627 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2026
Fort Tejon Solar
Solar + storage
617 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2019target 2026
Bullhead Solar
Solar + storage
600 MWWithdrawn / abandoned Clark, NVCAISO Apr 2019target 2023
Sloan Energy Center
Solar + storage
578 MWWithdrawn / abandoned Clark, NVCAISO Apr 2019target 2023
Grand Lake Hybrid Solar
Solar + storage
504 MWWithdrawn / abandoned Kings, CACAISO Apr 2019target 2023
SV Energy Storage Facility
Battery storage
500 MWWithdrawn / abandoned San Diego, CACAISO Apr 2019target 2026
Fokus Renewable Energy Center
Other
472 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2023
Big Duck Storage
Battery storage
462 MWWithdrawn / abandoned Fresno, CACAISO Apr 2019target 2022
Ranchero Solar
Solar + storage
450 MWWithdrawn / abandoned Colusa, CACAISO Apr 2019target 2023
Triumph Solar
Solar + storage
450 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2023
Trestles Energy Storage
Battery storage
434 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2019target 2022
Boulder Oaks Hybrid
Wind + storage
411 MWWithdrawn / abandoned San Diego, CACAISO Apr 2019target 2023
Doradus
Solar + storage
406 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Rigal
Solar + storage
406 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Ash Tree Hybrid Solar
Solar + storage
406 MWWithdrawn / abandoned Fresno, CACAISO Apr 2019target 2022
Familia Hybrid Solar
Solar + storage
405 MWWithdrawn / abandoned Maricopa, CACAISO Apr 2019target 2022
Garces Hybrid Solar
Solar + storage
403 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Agua Amarga Wind
Onshore wind
403 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2023
DRY Grape Hybrid Solar
Solar + storage
403 MWWithdrawn / abandoned Fresno, CACAISO Apr 2019target 2022
Yellow Hay Hybrid Solar
Solar + storage
400 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2022
Draco Solar
Solar + storage
375 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2023
Peony
Solar
359 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Journey Storage
Battery storage
355 MWWithdrawn / abandoned Kings, CACAISO Apr 2019target 2022
Barrenspring
Solar + storage
308 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2023
Vestal Valley
Solar + storage
308 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2023
San Bernardino BESS
Battery storage
308 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2019target 2022
Hinson BESS
Battery storage
308 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2019target 2022
Nikola Norte
Solar + storage
306 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2019target 2023
Tesoster
Solar + storage
306 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2019target 2023
Nikovaster
Solar + storage
306 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2019target 2023
Superba Storage 1
Battery storage
305 MWWithdrawn / abandoned Orange, CACAISO Apr 2019target 2021
Arcturus
Solar + storage
304 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2026
Sugarloaf Hybrid Solar
Solar + storage
303 MWWithdrawn / abandoned Fresno, CACAISO Apr 2019target 2022
Rancho 2 Energy Storage
Battery storage
250 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2019target 2023
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)