United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in CAISO (California) (2017 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Harquahala Flats Solar + storage |
900 MW | Withdrawn / abandoned |
| Mesaville Solar Solar + storage |
706 MW | Withdrawn / abandoned |
| Panoche Energy Center Gas |
432 MW | Withdrawn / abandoned |
| Westside Canal Energy Center Solar + storage |
425 MW | Withdrawn / abandoned |
| Creosote Solar |
419 MW | Withdrawn / abandoned |
| Golden Square Solar + storage |
410 MW | Withdrawn / abandoned |
| Canella 2 Solar Farm Solar + storage |
400 MW | Withdrawn / abandoned |
| Sourgrass Solar Solar |
380 MW | Withdrawn / abandoned |
| Ventura Energy Center Gas |
326 MW | Withdrawn / abandoned |
| Wardenclyffe Battery storage |
314 MW | Withdrawn / abandoned |
| Harquahala Sun Solar + storage |
313 MW | Withdrawn / abandoned |
| Hidden Hills Solar 1 Solar |
306 MW | Withdrawn / abandoned |
| Vision Wind Onshore wind |
281 MW | Withdrawn / abandoned |
| Longspur 10 Solar |
264 MW | Withdrawn / abandoned |
| Dasos 10 Solar |
210 MW | Withdrawn / abandoned |
| Perseus Solar Solar |
209 MW | Withdrawn / abandoned |
| Romero Creek Solar Solar |
204 MW | Withdrawn / abandoned |
| Vermillion Energy Storage Battery storage |
204 MW | Withdrawn / abandoned |
| Vanguard Solar BESS Solar + storage |
200 MW | Withdrawn / abandoned |
| Lotus 2 Solar Farm Solar + storage |
200 MW | Withdrawn / abandoned |
| Goldwick Solar Farm Solar + storage |
200 MW | Withdrawn / abandoned |
| Calhawk Solar Farm Solar + storage |
200 MW | Withdrawn / abandoned |
| Darlington Balley Solar Energy 1 Solar + storage |
185 MW | Withdrawn / abandoned |
| Munz Solar 1 Solar + storage |
180 MW | Withdrawn / abandoned |
| Wistaria Solar 2 Solar |
156 MW | Withdrawn / abandoned |
| American Kings 10 Solar |
156 MW | Withdrawn / abandoned |
| West Springs 2 Wind Farm Onshore wind |
155 MW | Withdrawn / abandoned |
| Sun Streams Solar 3 Solar |
155 MW | Withdrawn / abandoned |
| Quartzite 10 Solar |
155 MW | Withdrawn / abandoned |
| East-Bay-Wind Onshore wind |
153 MW | Withdrawn / abandoned |
| King Flat Wind Farm 1 Onshore wind |
152 MW | Withdrawn / abandoned |
| Firehawk Solar 1 Solar + storage |
150 MW | Withdrawn / abandoned |
| Exchequer Hydro |
112 MW | Withdrawn / abandoned |
| Blue Mountain Wind Onshore wind |
108 MW | Withdrawn / abandoned |
| Puerta Renewable Energy Reliability Center Solar + storage |
105 MW | Withdrawn / abandoned |
| Sage Solar Solar |
103 MW | Withdrawn / abandoned |
| Las Camas 2 Solar |
103 MW | Withdrawn / abandoned |
| Kerrness Solar Solar |
102 MW | Withdrawn / abandoned |
| Rubita Solar |
102 MW | Withdrawn / abandoned |
| Oakland Energy Reliability Center Battery storage |
102 MW | Withdrawn / abandoned |
| King Flat Wind Farm 2 Onshore wind |
102 MW | Withdrawn / abandoned |
| Gabriel Solar 3 Solar |
100 MW | Withdrawn / abandoned |
| Chanson Energy Storage Facility Battery storage |
100 MW | Withdrawn / abandoned |
| Kroe Hybrid Solar + storage |
100 MW | Withdrawn / abandoned |
| Wilbur Energy Storage Battery storage |
94.5 MW | Withdrawn / abandoned |
| Mallard Energy Storage Project Battery storage |
90.0 MW | Withdrawn / abandoned |
| Vickers Energy Storage Battery storage |
80.0 MW | Withdrawn / abandoned |
| Cassiopeia Solar Solar |
77.0 MW | Withdrawn / abandoned |
| Curry Solar Solar |
71.5 MW | Withdrawn / abandoned |
| Warren Solar 1 Solar |
71.5 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)302 Β· 46.9 GW
- SPP (Southwest Power Pool)162 Β· 32.0 GW
- MISO (Midcontinent)127 Β· 19.9 GW
- PJM (Mid-Atlantic, Midwest)236 Β· 18.3 GW
- Southeast (non-ISO utilities)208 Β· 16.9 GW
- CAISO (California)65 Β· 11.3 GW
- ERCOT (Texas)55 Β· 8,908 MW
- ISO-NE (New England)42 Β· 4,856 MW
- NYISO (New York)61 Β· 2,565 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)