Warren Solar 1

Warren Solar 1 is a 71.5 MW solar request withdrawn in the CAISO interconnection queue, in Nye County, Nevada, connecting to VEA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandonedMay 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1401
Grid region
CAISO (California)
Utility / transmission owner
VEA
Connection point (POI)
Charleston Substation 138kV
Location
Nye County, Nevada
Technology
Solar: 71.5 MW
Total requested
71.5 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
1 May 2017
Proposed online date
March 2020
Withdrawn
May 2018

Location

Marker shows the centre of Nye County; the queue data does not give exact sites.

Power plants in Nevada Β· Transmission lines in Nevada

Other requests in Nye County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem