United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Longspur 10

Longspur 10 is a 264 MW solar request withdrawn in the CAISO interconnection queue, in Kern County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandonedJul 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1422
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Rattlesnake Switchyard 230kV
Location
Kern County, California
Technology
Solar: 264 MW
Total requested
264 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
1 May 2017
Proposed online date
December 2021
Withdrawn
July 2017

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem