SOLAR Β· CAISO

Perseus Solar

Perseus Solar is a 209 MW solar request withdrawn in the CAISO interconnection queue, in Merced County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandonedJul 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1387
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Borden Substation 230kV
Location
Merced County, California
Technology
Solar: 209 MW
Total requested
209 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
1 May 2017
Proposed online date
August 2021
Withdrawn
July 2017

Location

Marker shows the centre of Merced County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Merced County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem