Wingtip Solar 1

Wingtip Solar 1 is a 2,352 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Merced County, California, connecting to PGAE.

Queue statusConsented
  1. PlanningQueued Apr 2021 (completed)
  2. ConsentedJun 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2032 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1943
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Los Banos 500 kV
Location
Merced County, California
Technology
Solar: 1,176 MW · Battery: 1,176 MW
Total requested
2,352 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
15 April 2021
Agreement signed
2 June 2025
Proposed online date
September 2032

Location

Marker shows the centre of Merced County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Merced County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem